A system stand can be realised in around four to eight weeks, an individual custom build in eight to 24 weeks depending on scope.
Detailed answer
The duration depends mainly on the construction method, size and equipment. As a guide:
- System stand: approx. 4–8 weeks
- Custom solution on a system basis: approx. 4–8 weeks
- Custom build: 8–24 weeks depending on scope
The schedule is usually determined by the decisions before construction: concept, approval of the 3D visualisation, graphic files and technical connections. The earlier these decisions are made, the smoother the implementation.