Building an exhibition stand is a tightly scheduled process. The time window is set by the trade fair organiser, and anything that goes wrong within it can hardly be made up before the fair opens. Knowing the process helps you plan realistically and avoid the most common problems.
The timeline: when stands are built and dismantled
Exhibition stands are usually built 1 to 2 days before the fair opens and dismantled the day after it closes. How long the build-up takes depends on size and type of build: a system stand up to 30 sqm is usually up within a few hours, a custom build needs 1 to 3 build-up days. Build-up and dismantling times are set by the organiser and cannot simply be extended.
Lead time: what needs to be decided when
- 16 weeks before the fair: commission a custom build, ideally 20 to 24 weeks.
- 10 to 12 weeks before: plan any ceiling suspension. At major fairs, registration deadlines close 6 to 8 weeks before build-up begins.
- 8 weeks before: commission a system stand.
- 4 to 6 weeks before: decide on rental furniture and standard technology, 8 to 10 weeks for bespoke furniture and LED walls.
- 1 week before build-up: deliver content for screens.
Common pitfalls during build-up
Hall access and delivery
Every trade fair has its own rules for delivery times, vehicles, floor protection and passes. Overlooking them costs time that is missing from the build-up window. EXFAIR applies to the organiser for contractor passes, access permits and delivery slots.
Several trades at once
Stand construction, electrics, media technology and furnishing often work side by side on the same space. Without a coordinated sequence, the result is waiting time and rework. EXFAIR's project management coordinates the trades on site.
Order power and connections in time
Exhibitors order power and other connections from the organiser, usually via the exhibitor portal. EXFAIR calculates the connected load, orders the power connection and handles the wiring on the stand.
Last-minute changes
Once components have been produced and loaded, dimensions, structure and power routing can hardly be changed on site. That is why every concept is agreed as a 3D visualisation before production. Changes at this stage are free of charge.
Fairs abroad
For fairs in Switzerland, customs clearance of the stand material is added, for example via Carnet ATA. The lead time for calling off a stand from storage then increases from 4 to 6 weeks.
Build-up checklist
- Check the organiser's build-up and dismantling times.
- Apply for contractor passes, vehicle access and delivery slots.
- Order power and other connections via the exhibitor portal.
- Register any ceiling suspension in time, with rigging plan and structural calculation.
- Decide on furniture, technology and screen content.
- Name contacts for build-up, show days and dismantling.
- Plan dismantling, return transport and storage if needed in advance.
Dismantling
Stands are usually dismantled the day after the fair closes, again within a fixed time window. EXFAIR dismantles carefully, checks every part and, on request, stores the stand in Villingen-Schwenningen until the next fair.
How EXFAIR handles the build-up
EXFAIR's project management leads the build-up on site at trade fairs in Germany, Austria and Switzerland. We schedule crew and delivery around the build-up window, order technical services in advance and coordinate all trades. You arrive at a finished stand. More: Assembly and dismantling and Storage & logistics.